October Photos:
The photos below show illustrate how the podium deck is being formed. Post tension cables are being placed followed by concrete poured on top. The next phase is to commence on framing.
Post tension cabling going in before the concrete is poured.

Pouring the concrete.

Half of the concrete slab for podium deck is completed. This was actually 2 pours, each taking 8 hours each. It then takes 3 days for the concrete to dry.

Framing has begun.

Framing continues on podium deck.

Concrete bring poured over post tension cables on second half of podium deck.